Powertech engineers proactively custom designed and produced the essential infrastructure for the installation of the transformers.
Powertech was tasked by our client to procure 4 new transformers to maintain critical energy supply to remote Northern Territory.
However, the procurement process faced challenges as the transformer manufacturer was unable to supply the necessary related equipment within the required timeframe.
In response, Powertech engineers proactively custom designed and produced the essential infrastructure for the installation of the transformers. To ensure our clients project ran on schedule.
Solutions Provided:
Transformer Procurement:
– Procured four 1.5 kVA Air & Oil Natural transformers.
Custom Oil Bund Skids:
– Designed & produced galvanized steel oil bund skids tailored to fit the transformers.
Assembly, Transportation & Installation:
– Assembled the transformers and ensured proper transportation of the transformers and associated equipment to the site.